SR 641

This project involves construction of a new Terre Haute Bypass on SR 641. Phases III and IV will be advancing through construction. Phase III involves a new roadway from Feroe Road to Riley Road with a new interchange in Riley Road. Phase IV involves a new roadway from the new Riley Road interchange to I-70 with a new interchange at I-70.

Design is currently underway and the right of way acquisition process began in April 2009 with Surveying. Right of way acquisition will continue through 2011 with construction beginning in December of 2011.